Regulatory

G98 Application

G98 is the DNO notification process for small-scale generation systems up to 16A per phase (3.68kW single-phase), allowing 'fit and inform' installation without pre-approval.

What is G98?

G98 is the Engineering Recommendation developed by the Energy Networks Association (ENA) that governs the connection of small-scale generation equipment to UK distribution networks. It applies to systems with inverters rated up to 16A per phase.

G98 Thresholds

Connection TypeMaximum Capacity
Single-phase3.68 kW
Three-phase11.04 kW

G98 vs G99

The key difference is in the approval process:

  • G98: "Fit and inform" - install first, notify DNO within 28 days
  • G99: "Apply and wait" - submit application, wait for approval before installation

G98 Process

  1. Install the solar PV or battery system
  2. Commission the system
  3. Notify the DNO within 28 days of commissioning
  4. DNO acknowledges the notification

When G98 Applies

G98 is suitable for:

  • Standard domestic solar installations (typically 3-4kW)
  • Small battery storage systems
  • Most residential renewable installations

If your system exceeds G98 thresholds, you'll need a G99 application instead.